Wellesley Community Centre Phase 2 – Pool Addition
Client
The City of Toronto
Budget
$18 million
Size
54,000 sf.
Completed
2020
Delivery Model
Design-Bid-Build
Sector
Multi-Use Recreation Facilities
Architect
MacLennan Jaunkalns Miller Architects
The site of the Wellesley Community Centre – Pool addition is located at 495 Sherbourne St, Toronto. The development area was approximately 1,600 sq.m. of the community centre site, bounded by a small landscaped area on the south, the existing community centre to the west, Bleeker Street to the east and the existing small community centre parking lot to the north. Construction included a 54,000 sf. indoor pool addition to existing facility including 5 lane x 25m training tank, leisure tank, hydrotherapy tank, change rooms, staff offices, multi-purpose rooms etc. Extensive sustainable “Green” features, including a green roof and geothermal systems.



The project’s site was especially complex due to the nature of the site being extremely tight and surrounded by residential buildings and connection to the adjacent Wellesley Community Centre that remained active throughout construction




Other Projects
View More ProjectsRouge Valley Community Recreation Centre
This project brings together a below-grade aquatic centre, fitness and wellness areas, multi-purpose community spaces, and a de...
Muskoka Lumber Community Centre
The Muskoka Lumber Community Centre brings together recreation, culture, and community programming within a single, fully integ...
Grimsby Peach King Centre
The Grimsby Peach King Centre renovation and expansion transformed the existing arena complex into a modern, multi-use communit...
Ridley College Iggulden Building and Athletic Complex
The completed project provides Ridley College with renewed academic, arts, and athletic facilities that bring together a wide r...